Sylvania CFA & Foundation Piling Project | Case Study NSW
Ormond Civil delivered CFA piling and foundation piling works in Sylvania, NSW, supporting critical early-stage construction and establishing the structural foundation system for future development. The project required the use of multiple piling methodologies, each selected to suit specific ground
Turner ACT Shoring & Foundation Piling Project | Case Study
Ormond Civil delivered a shoring and foundation piling solution in Turner, ACT, supporting excavation works within a constrained and technically demanding site environment. The project required precise coordination and execution of piling and anchoring systems, with additional complexities introduced by groundwater
Piling, Shotcrete & Capping Beam Installation – Wilton
Ormond Civil successfully delivered a comprehensive piling, shotcrete, and capping beam installation package for the Wilton Project in NSW. The works formed a critical part of the foundation and shoring system required to support ongoing structural construction. The project demanded precision
Blue Mountains, NSW
Ormond Civil partnered with Quickway Constructions to address slope instability along Bells Line of Road in the Blue Mountains, New South Wales. Following a prolonged and heavy rainfall event, the embankment adjacent to the roadway experienced significant instability, characterized by large tension cracks and vertical
Emu Plains, NSW
The project was a part of the NSW Government’s Commuter Car Park Program, providing more convenient access to public transport at key interchanges and helping to ease congestion on roads.Ormond Civil was engaged to undertake the Drilling & Installation of
William Drive Hill, ACT
William Slim Drive Duplication included widening the existing road corridor to allow multiple lanes of traffic in each direction. The duplication included a new bridge crossing over Ginninderra Creek.Ormond Civil Drilled & Installed 10 Quantity of 750mm Diameter Piles &
Australian War Memorial, ACT
The AWM redevelopment project was undertaken to increase exhibition space including creation of an additional underground level at ANZAC Hall, construction of the Bean Building & reconfiguration of the southern entry to the memorial.High-risk workshops were carried out with all stakeholders
Pitt Street Metro, NSW
Ormond Civil collaborated with CPB Contractors on the construction of the new Pitt Street Station in the Sydney CBD, part of the expansion of Sydney’s metro rail network.Following demolition and excavation of the site, improvement works were required to the
Gundaroo Bridge, NSW
The purpose of this project was to construct a new bridge accessway for the expanding population of Yass Valley.A development of 10 residential blocks was completed immediately to the north of Gundaroo and positioned around an existing earth fill dam.
Woollahra, NSW
Key project details:220 piles, ranging from 450mm to 750mm in diameter20 temporary anchors securing the foundation250m of capping beam installed1250m² of shotcrete for robust reinforcement10 braces ensuring structural stabilityThree seamless contiguous walls built to exact specifications.The project’s close location to